![]() |
|
|
|
| |||||||||||||||||||
|
Work Party at Ebridge LockSunday 26th October 2008THE PLAN. To cut grass and weeds from the chamber island and opposite bank; to clear trees from canal and bank to the north-eastern side of the canal.
WORK ACHIEVEMENT. Weather: seemed to have had communication problem with the weatherman as the rain did not stop by 11.00 but only got lighter! It did stop however by noon! Thereafter very bearable. Before Marc could join us, we had cleared some of the minor saplings and offshoots - the construction of an environmentally approved hedge started to take shape!
A very fruitful conversation ensued, to the betterment of all concerned.
When I rejoined the group of three others back at the tree area, David Tomlinson unexpectedly arrived - he's from about 200miles away and visiting the area so thought that he would join us for a while. Very good thought! Lunchtime was approaching and there lie the remains of three trees in the canal bed, unwatered of course. With the thought of changing into dry clothing and Caroles' cake in mind, we remained at the task until all was vigorously cleared - the little animal, bird and insect haven growing the while atop the bank!
Next work party will be at Bacton Wood Mill Lock on Sunday 30th November, followed by Honing Staithe on Sunday 28th December 08 and Briggate at the end of January 2009. |
|
|
Work Party at Briggate Mill PondSunday 12th October 2008THE PLAN. To burn the brash previously cut, to continue to clear back shrubs, trees and reed etc from the pond area and eventually locate the boundary of the pond.
WORK ACHIEVEMENTS. Weather: misty start to the day but not cold. The sun burned off the mist and the rest of the day was clear and warm. The pond on our arrival actually had some water lying on the bed! Not exactly what I would have liked, but it did not deter from the actions of the day. It is thought that the water, apart from the direct rainfall, had entered the pond from the canal, indicating that blockages in the main route are causing flooding, or at minimum not alleviating it.
Brian Wexler, (good to see you on site again Brian), took his leave and as we were all eating some of Caroles' finest culinary delight, Roger made an appearance - his nose homing in on the cake! So, duly refreshed, but slowed down by the usual ultra high calorific intake, we returned to the work front. The next work party will be at Ebridge on 26th October, and at Bacton Wood on 30th November with the last of the year at Honing Staithe on 28th December 2008. |
|
|
Work Party at Honing Staithe CutSunday 28th September 2008.THE PLAN. To check the state of the new permissive Walk; to clear the 'island' from the canal at the mouth to the cut; clear as much as possible from the cut; to install protective guards to the paddle chambers at Honing Lock; to generally clear up the site and make ready for the opening of the Walk.
WORK ACHIEVEMENTS. Weather: fine start to the day with clear skies, which did not last for too long with a shower at lunchtime followed by general cloud. A pleasant temperature in which to work. An amazing number of sixteen people turned up for the session!
The stretch of land to the left of the Cut (near to the road) is starting to look in good shape once the mower had been run over it! There were still a number of saplings, which do tend to grow into big trees, interfering with the general view so these were removed and some were used as an edging to the land. The spoil from the cut, which had been used as infill some seven months before, had settled into a good hard surface and plant-life has begun to return - in fact the whole scene looks quite green already. During the morning, Chris and Marc set off to carry out the task at Honing Lock (a H&S issue pointed out to the Canal Co by the Environment Agency) - returning, it seemed in record time!
Today was a little bit special for two reasons - firstly Chris is at the break in life called the 60th birthday and secondly we were expecting the North Norfolk MP Mr Norman Lamb to arrive and open the permissive Walk. All of our thanks go to Chris and Mary for providing the first class provisions for the lunch and Carole for doing her usual, body-enlarging temptations of cake and trifle! After his departure, we settled down again to work. It was a very inspiring sight to see so many figures bent over and clearing, cutting or tidying over a great area! At the end of a day, when so much had been achieved and a result actually seen, we departed around 17.30 to hot baths or showers! I am very proud to have been involved with such a team of volunteers and today was the culmination of so many hours of hard labour by so many over the past two years at Honing Staithe Cut. But, heh! - don't sit back too comfy, as there's more to do here yet!! The next work parties will be at Briggate Mill Pond on Sunday October 12th and at the end of the month at Ebridge on Sunday 26th October 08. Please note the change of this venue. The rest of the year remains unchanged as 30th November at Bacton Wood Lock and 28th December at Honing Staithe Cut/Honing Lock. |
|
|
Work Party at Honing Staithe CutSunday 12th October 2008THE PLAN. To continue the clearance of bushes, trees and fallen timber from the pond area and to burn the brash.
WORK ACHIEVEMENT. The weather was very kind throughout the day although the breeze had a cool edge to it. Mostly sunshine with some cloudy periods. During the afternoon, three new sites, on the pond bed, were set up for the burning of the newly acquired brash at the next visit. Useable logs were piled in stacks for collection at a later date. Now that it is visible over a fairly large area, the pond bed is found to be in a fairly level and sound condition, albeit many trees have rooted in it. During this work session, Mr Wm Cubitt paid a visit and a private discussion was held covering various items such as publicity, the opening of the walk at Honing Staithe and woods, work to be carried out at Honing Lock, the extent of the work to be carried out at Briggate Pond and the state of the public highway in connection with the pond. I was asked to provide some kind of barrier at the entrance to the pond site, which by now is getting to be quite open.
Later, our professional wood-working fellow, Alan with the Machete, set about cutting some forked supports to carry a suitably sized piece of timber to act as such a barrier. Chris cut an 18-foot straight-ish pole from the woods, dug holes to take the supporting posts and the barrier was duly erected! It is suitable to indicate that the site is NOT open for public entrance and IS a barrier for the unwary. Together with Peter, who constantly busied himself with cutting, carrying and tending to the fire, the seven of us present spent a very pleasant day, especially as the work carried out showed that progress was being made. My usual thanks to all who attended and as discussed on site look forward to seeing you there to follow up the progress on the extra date of Sunday 12th October. Next meeting is at Honing Staithe and Cut on Sunday 28th September 08. |
|
|
Work Party at Honing Dee Bridge and PathSunday 31 August 2008THE PLAN. To check the state of the path so far and open it onto the Weavers Way; to make a clear track through from the cut end, for the digger, as far as the newly constructed bridge over the backsoke; to burn brash on the north-western side of the Cut; to inspect the bank of the newly cleared canal between Dee Bridge and Honing Lock; to visit Honing lock and take measurements and details of fixing for the securing of the paddle chambers, (ref letter and photographs as received from the Environment Agency)
WORK ACHIEVEMENT. The weather was partly clouded all day but with a reasonable amount of sunshine, to make it a very pleasant day to be beside the canal! A total of eleven folk turned up and readily dispersed to various areas along the path, after the H&S and work briefing.
Chris and I walked the length alongside the newly cleared canal between Dee Bridge and Honing Lock. This was accomplished with some difficulty as the area, previously cleared along with the canal, had re-grown to a height of some six feet in places. The reason for taking this route was to establish if the canal was indeed still clear and also to note the amount of brash and other debris that will need to be relocated/burnt/stacked. In the event it was discovered that one tree with two trunks, had suffered a splitting of both trunks and the upper parts had fallen backwards into the water leaving only a clearance of about five feet by the opposite bank. On arriving at the lock, it was good to see several groups of canoes coming up to the winding hole at the tail of the lock. The next work-party is at Briggate Pond on Sunday, September 14th followed by Honing Arm and Lock on Sunday September 28th , when it is hoped to 'open' the new path. |
|
|
Work Party at Briggate Mill PondSunday 17th August 2008THE PLAN. To make a start on the total clearance of trees and other growth from the millpond area as depicted on drawings as supplied by Savills.
WORK ACHIEVEMENT. Weather. There seems to have been a glitch in communications as the heavens opened when started to clear the lock chamber bank! Even reverting to working under the canopy of the trees, did not prevent everyone becoming quite wet. At 11.30 the decision was made to take an early lunch and if the weather did not improve, a cessation of work would be called.
After the H&S and plan briefings, Marc and the new machine cut easily through the well overgrown lock chamber bank and made an access path into the millpond site proper. The first seven of us present started, variously, on clearing a work area near to the millrace culvert spill; clearing brambles etc from the roadside and taking down saplings. Peter and Fred arrived about lunchtime. It was found that the base of the pond seen so far is littered with the remains of trees, which have either been dumped or fallen over - some in a quite rotten state, and of no further use. Amongst the old mild bottles, Mary located a mug celebrating the accession to the throne of King Edward VII - sadly with a small piece missing from the rim! I am very pleased with the result of our first days' labours at this site and the dedication of The Team was exemplified today - Thank you all!
The following changed programme was agreed.
|
|
|
Work Party at Ebridge LockSunday 27th July 08
THE PLAN. To inspect the pond wall and guard rails, to clear the mouth of the lock and chamber island, to clear trees and obstructions from the canal bank on the north-eastern side upstream of the weir. WORK ACHIEVEMENT. Weather was first class with 9/8 sunshine and high temperature. Six stalwarts arrived for the start of 09.30 and after the H&S and task briefing for the day,
The lunch break came all too soon - what a difference good weather makes? This time, lunch was completed not only with Carole's cake but also her trifle! Only the very brave attempted to eat both! After all of this, we staggered back to the work on hand- Carole and Darren upstream of the lock mouth, Marc and Graham to the trees well upstream and Chris and I left to visit Briggate. Here we exposed most of the guardrail posts and rails. The wall was found to be in a similar state to that at Ebridge - please see my separate report. The next work party will be at Briggate on Sunday 17th August 2008. There is no meeting at the end of August as that is a bank holiday. There will probably be two meetings in September, details of which will be passed on to you when further information becomes available. |
|
|
to Build Soke Bridge at Honing Staithe Cut on the North Walsham & Dilham Canal.Saturday 19th July 2008THE PLAN. To construct a wooden bridge, according to instructions, over a soke to link the new footpath beside the canal and Weavers Way.
![]() WORK ACHIEVEMENT. Weather, cloudy with intermittent sunshine and very heavy showers. (It was a Saturday, after all!). The lorry with the flat-pack bridge on board arrived slightly after the planned time at 08.40. This was an unusually early start for us!
Following the H&S 'bit' and a quick briefing, we set to. The plans and equipment list had been prepared by a man, well experienced in this type of work and whose bridges span many a dyke in this region. However plans are plans and they do not allow for local situations and therefore before work could start on the bridge itself, a lot of discussion took place as to fixing the height above water level (actual now and planned, when canal is in better state of water when lock gates fitted at Honing lock), type of footings, method of fixings to prevent movement of bridge, etc. The remainder of The Team had also been very busy cutting and preparing stakes, logs, clearing brash, overhanging trees and removing the massive lump of earth covering the roots of a long-since fallen tree, which obstructed the main footpath. A well-earned lunch was taken at the Weavers Way end of the Staithe Cut with bright sun shining off the waters of the cut making the scene very pleasant and relaxing. I don't think that Carole's cake should really have been eaten, as I swear that it slowed everyone down in the afternoon! But it was worth it!! After lunch, Alan (our trade carpenter) arrived and with David K and me completed the construction of the bridge and laid and stapled the wire netting onto its surface. This done, it was now the time to earth up the approaches at each end of the bridge and the massive lump mentioned above was used for this purpose. Just to prove that the bridge is manly enough, most of us stood on it with a loaded wheelbarrow to have our photo taken. Needless to say, it did not budge of course! This achievement is quite notable as it is the very first project, which has been funded by the new Canal Trust! Again, my thanks go to all members of The Team for their wonderful support and skills exhibited on site. Please remember that this was the first successful construction project - there will be many more to come! The next work party is on Sunday 16th August 2008 at Briggate Lock site. Have a lye-in for these, as they do not start until 09.30! |
|
|
Work Party between Honing Dee Bridge and Honing LockSunday 15th June 2008.THE PLAN. To continue the work commenced on Sunday 15th June 08 to clear the canal of obstructions and growth.
WORK ACHIEVEMENT. Beautiful sunshine with a light breeze even at 8am and enough heat to make working in the deep shade a delight. Short shower of rain at end of day.
The Work Party began their efforts earlier than usual as there was a huge task ahead and subsequently a later finish of 18.00 was recorded. The Work Party stayed as one group on this occasion and commenced from the Dee Bridge end. I had appointed Marc Lines as Work Party Leader, in my absence, for the day. Marc read out the H&S bit first and then outlined the plan for the day. By the end of the day, and with lots of aching arms, legs and backs, the whole quarter of a mile stretch of bank and canal between the Dee Bridge and the Lock had been cleared. Marc even controlled his 'work-boat', suitable named “Marc 1”, using a single oar and luck, through the cleared section. As expected, the level of the water has dropped following the removal of the blockages, but the flow rate has (seemingly) increased. I am indebted to the eight members of the Team; Marc as Leader, Alan, a very valuable and new-ish member (Man with the Machete), Carole, Chris, Ivan, Jackie, Mary and Roger for their dedicated approach to this work and their combined achievement - a remarkable feat! I also thank Marc and Carole for sending me the basis of the above report
| |
| |
|
.
I shall be contacting you all re possible variations to the planned work-parties due to changes in circumstances. |
|
|
Work Party at Briggate Lock and MillpondSunday 18th May 2008THE PLAN. To locate boundary of the Mill Pond; locate wall adjacent to public roadway; cut down grass, nettles etc, prune trees as required.
WORK ACHIEVEMENT. Weather sunny all day with the occasional cloud passing over; light breeze; quite warm. After the usual briefing, Carole, Darren and Marc set to by cutting down the grass on both banks, avoiding the danger area on the east chamber side. Chris, Mary and David set off up the canal bank to make an assessment of the millpond boundary there.
Further work was then carried out at the Worstead end of the Mill Pond. This would indicate that the area is neither unattended nor wasteland. Chris, Mary and I then proceeded to the area and some spadework was carried out to reveal part of the end of the pond/roadway wall and an access was made to clear nettles and other plant growth in the pond area. The top of the wall stone was marked 'NWDC WALL'.
After a sunny lunchtime break taken on the west chamber bank and terminated by a large slice of Carols' very, very tasty cake (no whipped cream though!), we all applied ourselves to pulling the west tailgate back into its' metal, shaped 'hinge' post. Using a tirfer, ropes and levers this was safely achieved, when a second restraining chain was fitted to the gate, to supplement the original. Due to various obstructions, both on the gate and in the chamber, the gate could not be pulled completely into the reveal.
The spill frame taking water from the Mill Pond to the mill wheel race was cleared into a tidy state and some local trees were pruned to improve access. Building work and a safety check of the culvert would need to be carried out before this facility could be put to use again. During the day, several local people stopped and discussed what we were doing and, with diplomacy in mind, we were happy to talk of some plans we had. Some just said 'thank you for what you are doing' but did not stop. All together a very favourable and appreciative feeling was received from the local folk. |
|
|
Work Party at Honing Staithe CutDate: Sunday 27th April 2008.THE PLAN. If time allowed and weather permitted, to burn brash etc on the upstream side of the cut; to further clear the path alongside the canal; to clear more trees and branches from the canal itself alongside the pathway.
WORK ACHIEVEMENTS. Weather generally sunny with a light wind and a slight amount of rain later, which did not interfere with the proceedings; no burning carried out due to time restrictions. Eight people attended the work-party with an extra two adults and two younger boys present.
Darren took up much of his time in dredging that which he could of the tree-free waterway. This is not easy work! Darren and Peter also moved several large and awkward trees over to the other bank and up the steep slope as under-mud obstructions prevented them from being brought to the near shore. A much needed lunch break was taken in the 'tree-trunk' area. In conclusion, it was an amazing day with lots of concentrated effort by all concerned being thoroughly motivated - and exhausted by the end of the day! Marc proved an excellent leader with attention to H&S and conducting the requirements of the day in an efficient manner. I am indebted to Carole for providing me with the report. My thanks go also to all who persevere with this work and these few words can hardly do justice to the efforts that all have made. We are, however, beginning to see some progress, with hopefully a further stretch of water to be opened soon. |
|
|
Subject: Work Party at Ebridge LockDate : Sunday 23 march 2008.THE PLAN. To locate a wall shown on an old photograph, which appears to run parallel to the lock chamber wall and forming an edge to the Mill Pond: to expose the wall adjacent to the public roadway: to remove debris from the tail of the lock: to check an access way along north east bank upstream of the weir. WORK ACHIEVEMENTS. Weather fine and sunny all day with some fairly sparse high altitude clouds - quite warm with the hint of a breeze at times. The grass was cut on the southwest bank of the lock whilst three others started to locate and subsequently expose part of the Mill Pond wall alongside the public road (B…).
The two trees, brambles etc were trimmed back, on the pond side only, to allow easy access along the whole length of this wall. The condition of the wall is very good at low level but naturally the coping and upper course or three will need rebuilding. The guardrail mounted on concrete posts between the pond and public road is mostly all there but the concrete posts will need re-setting.
This wall was exposed up to where it was expected that a corner would lie and therefore hoping that it would lead to the missing wall. Two other members had been digging, in the approved manner when seeking a wall or staithe! but without success. They did however reveal a corner wall with a return, which headed for the BT telegraph post! But it didn't make it that far! The corner wall unit was eventually linked to the roadside wall but it went no further. Another consideration came to mind -did this return wall form one edge of a slipway into the Mill Pond? Both before and after lunch break, trial digs were carried out all over the place, and in various locations, but without the ultimate longed-for success of locating the edging wall. It will be a lot easier and much quicker with a digger! In the meantime, Roger the Waterbabe had been recovering numerous items of debris, including angle irons, which had been forcibly pushed into the lock tail bed and parts of plastic warning/fencing boards. He also noticed a mooring ring let into the wall of the mill building opposite the old water pump site.
Towards the end of the morning we had a visit by a Mr Graham Eckersley, an IWA member, who brought a rare collection of photographs - mainly of Ebridge. He says that he has bundles more of such prizes! The Norwich branch of the IWA, which was set up in the sixties, had carried out some work parties in this region some years ago.
Our well-earned lunch break was taken amongst the reeds on the base of the Mill Pond (we had been there before) in glorious warm sunshine! Nobody really wanted to move after Caroles' wonderful cake (we would not have been able to move if the portions had remained the size as cut by Jackie!) but needs must and we returned to the work face.
To sum it all up, it was a disappointment that the missing wall was not located but on the more positive side the pond side wall is shown to be in generally good condition; there may be a slip into the Mill Pond; the tail of the lock is cleared of major obstructions leaving a good uninterrupted flow of water; a path is clear on the east bank - and, perhaps more importantly, the Team of Eight had a thoroughly enjoyable day out in the sunshine and fresh air.
![]() |
|
|
Work Party at Honing Dee Bridge ArmSunday 24th February 2008.THE PLAN. To prepare and leave the east bank clear of brash and a strip footpath way basically levelled; to clear the hedge at head of arm alongside the Weavers Way; to dredge back as much as possible along west bank; to open block at mouth to re-admit water to arm.
WORK ACHIEVEMENTS. Weather. Sunny during a.m. becoming overcast in p.m. with occasional drizzle from 16.15. Tom and Digger moved along west bank clearing several logs and plenty of spoil leaving the bank in a fairly straight and acceptable state.
Several further leaning trees were also removed due to H&S and/or effect. A few old tree trunks have been laid along the line of the fence-posts (on Canal Co land) to be used later as bank edging. The above does not really describe the tremendous effort put in by everyone on site. Unfortunately the path outline did not get levelled due to shortage of time. There are still some patches of reed in the canal proper and in the arm as they are out of reach of the digger. These should be removed later in the year using the manual dredger bucket - or, of course, by the EA doing their work and dredging the canal for effective drainage purposes? SUMMARY. All of the brash which we had previously unwittingly placed on land behind the fence posts near to the foot of the road embankment (NCC Highways Department) has been removed and disposed of as has that placed along the rest of the arm east bank, leaving a relatively clear and tidy stretch of land. The odd sapling or tree may need to be removed in the final count and the bank needs to be completed and levelled. No further work was attempted on the canal-side pathway today.
More than a score of visitors had stopped and chatted and the only comments were good ones! As the literature at the entrance to the arm now includes the NW & D Canal Trust, as well as for the EAWA, more questions were asked. Carole (Secretary to the Trust) took membership forms and fees for the Trust from several people, which is quite encouraging. ![]() |
|
|